LTC 165-2008 Update on Public Baywalks~ ~~~ I ~ ~ e
~ ~ ~t ~~ ° ~i ~~ i
OFFICE OF THE CITY MANAGER
LTC 165-2008
LETTER TO COMMISSION
TO: Mayor Matti Herrera Bower and Members of the City Commiss~ n
FROM: City Manager Jorge M. Gonz
City Attorney Jose Smith
DATE: June 20, 2008
SUBJECT: Update on Public Baywalks
The purpose of this LTC is to update the Mayor and City Commission on the status of the
baywalks at the rear of the Waverly, Flamingo and Bentley Bay Condominiums.
WAVERLY
The Waverly (formerly the Parkshore South Beach) project was approved by the Design Review
Board (DRB) on August 5, 1997 (DRB File No. 9024). Since the original approval, the existing
structure has become legal non-conforming in terms of overall height, FAR, parking and with
regard to the parking pedestal design. Condition 11 of the Final Order for the project states the
following:
A Baywalk extension, from the south side of the property north into the future park area,
shall be required.
Although a Baywalk was constructed in accordance with the DRB Final Order with direct access
from 14th Street, a fence was installed along the north property line to prohibit public access to
the Baywalk.
The Waverly's request to clarify Condition 11 of the DRB Final Order, and keep the Baywalk
closed to the public until a Baywalk was constructed on properties to the south of the Waverly,
was denied by the DRB on October 3, 2006. A request for a re-hearing of the action taken by
the Board was denied by the DRB on May 1, 2007. On May 22, 2007 the applicant filed an
appeal of the DRB decision to the City Commission. On October 17, 2007 the City Commission
denied the applicant's appeal of the DRB decision. The Waverly thereafter filed a petition for
writ of certiorari of the Commission's action to the Appellate Division of the Circuit Court.
The Special Master heard argument on March 31, 2008 on the City's request to remove the
fence and repair the Baywalk pending permits being issued and the contractors mobilized to
repair the seawall and installation of the security fence. The Special Master denied the request
because the Waverly represented that the permits will be issued shortly and work will
commence within 30 days thereafter, and completed within 120 days of commencement.
Update - Mav 15, 2008:
On April 17, 2008 the Special Master held a hearing for the purpose of receiving a progress
report on the status of permitting the seawall and fence improvements. A representative for the
Waverly reported that its engineer is working on drawings to respond to Public Works'
comments, and will resubmit. Such resubmittal occurred, but further corrections to the
plans were still required before Public Works could sign off on the permit. Code Compliance
We are committed to providing excellent public service to all who live, work and play in our vibrant, tropical, historic community.
LTC -Update on Public Baywalks
Date: June 25, 2008
Page: 2 of 3
staff reported at the hearing that they did a site inspection and produced pictures of the then
current status; more of the baywalk is excavated and closed off, but not all. Staff inspections
since then have indicated the Waverly residents are using the portion of the baywalk not closed
off. The City Attorney's Office raised the concern about the Corps of Engineers' review, and that
separate applications for permits for security fence and gate need to be prepared and filed so
that all work can occur expeditiously, and asked for proof of filing before next hearing. The
Waverly representative said they didn't have information on the COE review, and thought that
the applications for security fence and gate were filed, and if not would comply. In addition to
Rosa de la Camara, Esq., representing the Waverly, Board member and Treasurer Enrique
Tejera also appeared; he stated that they would do the work despite financial burdens due to
unit foreclosures and other issues with building. The Special Master will rehear the case May
22 at 6:OOpm
The City Public Works Department has completed its review of the plans and provided important
comments several times to the Waverly engineer of record. As of May 7th, Public Works
approved the revised plans and the engineer of record has been notified in order to proceed for
a City building permit. He will then take the permit to DERM and the COE for final approval.
Update -June 25, 2008:
In a decision issued June 6, 2008, the Appellate Division denied the Waverly's petition
challenging the DRB's and Commission's interpretation of the condition. The Waverly argued
that it need not open the baywalk at this time, because the condition required that a baywalk to
the south of the Waverly first be constructed and opened. The Waverly argued that the absence
of a connection to the south raised security issues, which justified the delay until such a
connection was completed. The Court found the DRB condition was clear and unambiguous,
meaning that no connection to the south was required before the Waverly's baywalk should
open to the public, and that the City provided procedural due process, observed the essential
requirements of law, and its decisions were supported by substantial competent evidence.
The following permits have been issued for seawall repair: The City of Miami Beach building
permit was issued May 19, 2008. The DERM permit was issued May 22, 2008. The Army Corps
of Engineers permit was issued May 29, 2008. The Waverly Association has agreed, and
represented to the Special Master, that it will mobilize and commence construction by 30 days
from the date of the last permit is issued.
FLAMINGO
The Grand Flamingo project was approved by the Design Review Board (DRB) on November 4,
1997 (DRB File No. 9191). Since the original approval, the subject project has become legal
non-conforming in terms of overall height, FAR, parking, and with regard to the parking pedestal
design. Condition 9 of the Final Order for the project states the following:
A Baywalk extension, from the south side of the property north into the future park area,
shall be required.
Although a Baywalk was constructed, fences have been installed blocking public access. The
Flamingo has raised serious concerns and legal issues related to the language of the final order.
We have determined that this language, and other documentation surrounding the approvals,
require the Flamingo's Baywalk to open to the public when the project to the north (Mae Capri)
opens its Baywalk to the public, which should occur in July. We have consulted with outside
litigation counsel, due to the complexity of the issues, and they agree with our conclusion. At
LTC -Update on Public Baywalks
Date: June 25, 2008
Page: 3 of 3
that point we will remind the Flamingo of its obligation to open its baywalk to the public. If it fails
to do so, the City will take the appropriate legal action.
BENTLEY BAY
At this time, staff reports that City records indicate that the existing baywalk behind the Bentley
Bay is not part of any development review order. Staff also reports that this project was not
required to be reviewed by the County's Shoreline Review Committee, and thus the baywalk was
not the result of any action by that Committee.
The administration has reached out to representatives of the Bentley Bay's Condominium
Association and begun to discuss ways on how to remove the wall on the north side of the
property.
It should also be noted that there may be opportunities in the future, as the ground floor
commercial space located at the Bentley Bay comes on line, to further explore opportunities
relative to removal of the wall and access by the public to this private baywalk.
`~
JM H
T:WGENDA\2008Wune 25\Regular\Baywalk Update LTC 6-25-08.doc
C: Gary Held, First Assistant City Attorney
Bob Parcher, City Clerk
Jorge G. Gomez, Planning Director
Thomas R. Mooney, Design and Preservation Manager
C'7 rv
c.,
_-~ ~
-< ~ ~
'+~
r- tv `~
-' o ''1`7
L ; -o ,~
° ~ -~
~ N
.C~
r,~ C.l'1