089-2001 LTC
CI i Y 0 F M lAM I BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
http:\\ci.miamj..beach.fl.us
L.T.C.No.?1-;J.oo I
LETTER TO COMMISSION
May 9, 2001
TO:
Mayor Neisen O. Kasdin and
Members of the City Commission
FROM:
SUBJECT:
Jorge M. Gonzalez ,.1/
City Manager ~ 0
COLLINS AVENUE CONSTRUCTION PROJECT
At a recent Collins Avenue Task Force Meeting several issues were raised by the business
community relative to the impact of construction on their businesses. Three principal issues were
addressed at the meeting including time of completion of the segment of Collins A venue from
Lincoln Road to 17th Street, signing to direct pedestrians to the businesses and the rate for parking
meters in the immediate vicinity of the construction activities.
In addressing the concerns raised, the following actions have been taken:
1. The Florida Department of Transportation (FDOT) has worked with the merchants and hoteliers
to identify appropriate signing needs and is in the process of having the signing prepared. The
City will follow-up with FDOT by May 11, 2001, to ensure that the signs are installed as antic-
ipated and that the merchants and hoteliers needs are properly addressed.
2. Given the extraordinary scope and magnitude ofthe project, the City has determined that some
limited and targeted meter reductions would be appropriate. Under my authority, I have made
arrangements to have the meters bagged in target areas during the normal daylight business hours
to offer some minor assistance to the merchants as a result of construction impacts. Parking in
these areas would be free for a two hour period and will commence on May 14, 2001.
3. The City has a very limited ability to affect the five week time of completion of the construction
within the immediately affected block from Lincoln Road to 17th Street. The contract that
FDOT has with the construction firm on the Collins A venue Project provides a window of
allowable operating hours from 9:00 a.m. until 9:00 p,m. The hours of operation are permissive
not manadatory. This specific time period was negotiated with the merchants and hoteliers and
agreed upon by the Commission in advance of the start of construction on Collins Avenue.
-..-.,'"
An important part of the contract, was also to require the construction firm to be completed with the
entire project by December 14,2001. To meet the December 14 completion date, this section of the
roadway has to be completed in a five week period. The five week schedule is part of the expedited
construction schedule to address and to mitigate negative impacts on affected hoteliers and
merchants in the immediate vicinity. At the present time, the contractor is operating within the
allowable hours and is operating on a schedule that will satisfy the five week construction period
specified in the construction contract. In the event that the contractor's completion time is
jeopardized, it would be our expectation that added hours would be worked.
Merchants in the immediate vicinity have been extremely frustrated that the contractor is not
working the full 12 hour time period that is available for construction thereby expediting
construction and completing the segment in less than five weeks. Unfortunately for the affected
merchants and hoteliers, the construction company is working within the contract parameters and
it is not within the ability ofFDOT or the City to compel them to work additional hours to complete
the project in a more expedient fashion. From the contractor's perspective the project was bid with
a specific timetable in mind and the contractor's costs of completing the work within the designated
time period were built into the bid that was subsequently awarded by FDOT for the project. If the
contractor alters the method of construction or adds more resources to further expedite the
construction, the contractor will incur unintended and unplanned expenses.
My staff is working closely with the Collins Avenue Task Force and has both solidified and
strengthened communication channels so as to rapidly identify issues and to implement mitigation
measures where possible in the construction corridor.
JM~ ~sam
F:\CM~1i1:~~\COLINLTC.WPD
, J.
CITY OF MIAMI BEACH
OFFICE OF THE MAYOR & COMMISSION
MEMORANDUM
TO:
JORGE M. GONZALE
CITY MANAGER
\,.
,I
FROM:
LUIS R. GARCIA JR.
VICE-MAYOR
DATE:
MAY 3, 2001
RE:
COLLINS A VENUE CONSTRUCTION PROJECT
At today's Business Advisory Committee meeting the fol1owing issues were discussed which
require immediate attention:
D The agreement hammered out after many meetings with the affected hoteliers, merchants, FDOT
representatives, contractor of the project, City administrators and myself that the contractor's
working hours would be from 9:00 a.m. to 9:00 V.m. The reasoning is that the longer hours the
crews work daily, the sooner the job will be completed and the adverse economic impact
lessened. However, the work crews are working ONLY until 6:00 p.m. The reason offered by
the contractor was financial. This is unacceptable. This project is deeply affecting the economy
of the area and endangering the livelihood of our hoteliers and merchants. The anticipated
adverse impact was estimated to be over 50 million dol1ars in the next two years. Since the City
Administration was so forceful in lobbying for this project to proceed, it is your responsibility
to insure that it is done correctly and expeditiously.
D Furthermore, I am requesting that an amendment to the ordinance be placed to reduce the cost
of the parking meters to reflect 30 minutes for .25
Please advise.
LRG/ept
381.::1:10
'2 iP!:'J'r!tWI.}) 11"
"",-," ,,>; \., J
C: Mayor and Commissioners
&~ :~ Wd &- ~VW 10
l::"J .;:.L
.. ,....; , ""0
-""."