LTC 250-2008 Normandy Shores Flooding Conditionsm MIAMI BEACH Z~~80Ci -3 AtS~I;S~
c r~7,.,
OFFICE OF THE CITY MANAGER
NO. LTC # 250-2008 LETTER TO COMMISSION
TO: Mayor Matti Herrera Bower and Members of the City Commission
FROM: Jorge M. Gonzalez, City Manager ~--- i~
DATE: October 2, 2008
SUBJECT: Normandy Shores Flooding Conditions
The purpose of this Letter To Commission is to provide the Mayor and City Commission with
an update on recent extraordinary Flooding conditions experienced in the Normandy Shores
neighborhood and Normandy Shores Golf Course, as well as the countermeasures
implemented to address these conditions. The conditions of this event were such that
Commissioner Libbin and I made a specific visit to the site to get a personal observation of
the situation. An emergency plan to address the situation was in place however, I directed
and authorized additional measures to be implemented to further ameliorate the condition as
quickly as possible.
Normandv Shores Neighborhood ROW Imarovement Project
Flooding Conditions and Countermeasures
Flooding conditions have been experienced intermittently during construction in recent
weeks, primarily as a result of extreme rain events and the unavailability of the existing storm
drainage system due to the replacement system being constructed. This has been an added
inconvenience to the residents and the contractor has been using vacuum trucks to pump
out and dispose of the accumulated stormwater runoff. Unfortunately, a number of factors
contributed to even worsening flooding conditions more recently; primarily centered at the
intersection of South Shore Drive and Hagan Street and extending to the east and west.
These factors included super-saturated ground from lastweek's rain events, additional runoff
from a high intensity rain storm on Sept. 30, as well as an extraordinarily high tide several
inches above normal that has triggered local flooding conditions throughoutvariouslocations
in the City and is expected to continue to peak in mid-October. High tides, in some cases,
have overflowed over seawalls in some areas of the City.
The confluence of these conditions culminated on October 1~` with the most extreme
stormwater flooding conditions experienced at the South Shore Drive and Hagan Street
location, and its mitigation required the partnering of both City and contractor resources,
utilizing emergency discharge measures into the ouffall system and directly into the bay to
remove excess floodwaters at the most affected locations by late afternoon.
The emergency resources dedicated to implement the countermeasures include three City
vacuum trucks and a 4-inch City pump, and a vacuum truck and 12-inch pump provided by
the contractor. The 12-inch pump will be left on stand-by at the subject location in the event
that future storm events trigger additional flooding. Once the new stormwater system is
completed, the structures and piping will be cleaned to address any concerns from
emergency countermeasures implemented.
In addition to the countermeasures mentioned above, two priority initiatives are underway to
Normandy Shores -Flooding Conditions
October 2, 2008
Page 2 of 3
reduce the impact of future extreme rain events prior to the completion of the neighborhood
project. The first is the re-allocation of resources to fast track the completion of the Hagan
Street stormwater system (within five weeks); this will make it possible to relieve future
flooding conditions by pumping into the new stormwater system if needed. The second
priority initiative will be to explore alternate construction methods that may help to reduce
construction time for South Shore Drive.
Construction Status
Project construction with the replacement contractor commenced in January, 2008 with
construction duration anticipated at 18 months. Initial construction has focused on the
stormwater system, and to date, over 50% of the stormwater inlet structures and connecting
piping for the entire project have been installed -primarily along South Shore Drive and the
majority of Fairway Drive. All of the 10 gravity wells have been completed, and at the cross-
streets to South Shore Drive, the following improvements have been completed (see
attached map):
• Rav Street: The well has been completed, detention and well boxes installed, and the
outtall completed.
• Haaan Street: The well has been completed, detention and well boxes installed, and
it is anticipated that the new outfall and seawall will be constructed within five weeks,
barring any major interruptions due to extreme weather conditions. In addition to the
outtall, part of the seawall is being reconstructed. Once the outfall at this street end is
completed, the contractor should be better able to relieve future flooding conditions
by pumping into the new stormwater system at this location and at Ray Street.
• Jones Street: Only the well box has been installed. Once the Hagan Street
stormwater installations are completed, work will proceed with installing the retention
box and outtall at this location which will be used to mitigate flooding. Completion is
expected by year end.
Construction completion of South Shore Drive, and its cross streets, will receive top priority.
Once construction of the stormwater system, including valley gutter installation, is completed
along South Shore Drive, then the contractor will proceed with the road construction work
and apply the first level of asphalt paving. At that point, general site conditions and
accessibility will have been greatly improved and, although the stormwater system will not
have achieved final certification, it will be available to address any extraordinary flooding
conditions that may arise. Presently, City staff, the consultant, and the contractor are
exploring altemate construction methods that may help to reduce construction time for South
Shore Drive and it is anticipated that a recommendation will be presented for review during
the week of October 6"'. Construction of the South Shore Drive section -through the first
level of asphalt pavement -should be achieved by late fourth quarter of 2008.
Construction will then proceed to the completion of Fairway Drive, where the stormwater
structures, connecting piping, and the first level of asphalt have been installed. The
installation of the stormwater system along North Shore Drive will follow. Concurrentwith this
work will be the installation of the pending retention and well boxes, as well as reconstruction
of pending outfalls along North Shore Drive. It is anticipated that construction of the North
Shore and Fairway Drives section -through the first level of asphalt pavement -should be
achieved by late second quarter of 2009.
The project is estimated to achieve substantial completion, including installation of
landscaping and decorative lighting, by August, 2009.
Normandy Shores -Flooding Conditions
October 2, 2008
Page 3 of 3
Normandy Shores Goff Course
Similar to the Normandy Shores neighborhood project, the Golf Course has experienced
extensive flooding conditions as a result of recent extreme rainstorms, in combination with a
number of factors thatwere previously described above. In addition, the flooding conditions
are worse than would occur during normal circumstances due to fact that the operating
permit for the storrnwater injection well system has not been yet issued to the City by the
regulatory agencies.
The reason for the operating permit delay is due to a requirement, from the regulatory
agency, for the City to install an additional monitoring well to test and review regularly the
waters at the golf course for chemical contents and is based on previous lake water sample
results reviewed by the agency during construction. The regular testing and the possibility of
a monitoring well installation was always a condition of the permit for the drainage wells
system at the golf course.
Consequently, the City has resubmitted a permit modification package to address the
monitoring well installation. Following approval of the submittal, the monitoring well will be
installed to meet the requirement for the operating permit. Allowing for the typical thirty day
agency processing time, the review process should be completed before the end of October.
Assuming that no additional modifications are requested by the agency, construction of the
monitoring well should be completed within two weeks after approval. The City and the
consultant are making every effort to expedite the process. The operating perrnitwould then
be received following a final inspection by the agency.
In addition, as previously reported, the City and the consultant have worked with the
regulatory agencies to add some modifications to the overall drainage of the golf course in
order to alleviate the current flooding experienced. One of them is the lowering and
enlarging of the drainage weir at the lake drainage structures that eventually direct flows to
the pumps and drainage wells. This is being done in order to enhance the flows and speed
with which the water is evacuated from the golf course and the lakes. These modifications
have been submitted for approval and the City and consultant are also working with the
agencies to expedite. As soon as approval is provided the installations will be made
promptly.
Finally, the modifications to the swales at Fairway and behind the homes in South Shore
Drive, which do not need approval from the agencies, will be commencing next week and
expected to be completed within a few weeks. These modifications should alleviate the
flooding of the Swale behind the homes as soon as they are completed. The Swale at
Fairway will not fully alleviate conditions until the neighborhood drainage system is fully
operational. The completion of the drainage system at Fairway and North Shore is expected
sometime in the late spring or early summer of 2009.
Please let me know if you have any questions or concerns.
attachment
C: Tim Hemstreet, Assistant Ciry Manager
Robert C. Middaugh, Assistant City Manager
Jorge E. Chartrand, CIP Director
Fre kmann, P.E., Public Works Director
JMd~`0 Ch1JCC
Facmgfe$ALL'~LTCASWormandy Shores Flooding LTC 2008.10-02.doc
n-.~
:~
afl
ff
a